There were angry scenes as subcontractors tried to retrieve their tools from a locked building site of a major WA construction firm, which yesterday flagged financial difficulties, sending shockwaves through the industry.

Cooper & Oxley, which has worked on both private and government contracts worth hundreds of millions of dollars, sent a letter to subcontractors advising them to cease work as the company was not in a position to pay them.

The letter, seen by the ABC, said the firm was reviewing its financial viability.

Several subcontractors returned this morning to the 500 Hay Street site in Subiaco — a partially built hotel, office space and restaurant precinct demanding access, at one point pushing over a fence, as private security guards tried to stop them taking tools and equipment.

Police officers arrived and told the guards to let the workers in, saying they were entitled to their tools.

Tradies left blindsided

Ceiling fixing apprentice Sam Hodges said he had only just paid off his tools, so was relieved to be able to retrieve them.

"I came to work on Monday morning, and before I could even get in my mate called to say they had locked it up," he said.

Ceiling fixer Liam McGill had been working on the project for more than a year.

He said he had always been paid on time and had no idea the lockout was coming.

When he arrived this morning, security told him he could not enter.

"They were just saying you can't come in, it's trespassing, and we said it's hardly trespassing … we're not trying to steal tools, we're just trying to get our own tools," he said.

Offers of help refused

The project's owners, Singapore-registered firm Dradgin, said in a statement they were unaware the shutdown would occur, and were "very disappointed" with the current situation.

"All payment terms and conditions of the contract have been met by Dradgin Pte Ltd," the statement said.

"In fact, Dradgin offered financial assistance to Cooper & Oxley to help Cooper & Oxley meet its obligations, unfortunately this was not accepted.

"Dradgin's priority is working with all parties involved — including subcontractors — so that the project may be completed as soon as possible."

WA Premier Mark McGowan said it was "pretty rotten" that workers had been locked out.

"Locking the gates, so people couldn't go and get their tools, was pretty bad and I expect people would be very upset by that," he said.

"I don't know if it's lawful or not."

Cooper & Oxley today issued a one-line statement, saying it was making arrangements for all subcontractors to collect their equipment and hardware from their sites.